Setting guide or oriented devices is to ensure the right sheet pile axis after construction, oriented pile or guide beam could be replaced by profile steel or wood, the spacing between the beams is just the width of sheet pile walls. In order to maintain accurate distance, between the beams, we can embed a temporary skids at certain intervals. After use, guide or oriented devices can be removed for next section’s use.
How to set ?
Use two section steels as oriented control clamp, place and fix it in position. In case of shock must re-adjust to fix it. In the driving of steel sheet pile, generally we need to send pile to the required elevation first, at this time, should remove the fixture first then gradually lift the pile.