Firstly, after the arrival of sheet piles, check whether the model is consistent as design, if not, re-calculate the strength and support of sheet pile.
Secondly, when go into the construction site, all sheet piles are required for inspection first, only a complete and straight sheet pile can be brought into the scene. For used-piles (like steel sheet pile), particularly should emphasis on inspection. Because used sheet piles in Pile, transportation and stacking process are easily deformed by external factors. If do not check, some may not easy to pile or drive.
Inspection method
Use a little flat car with a 1.5 ~ 2.0m long standard sheet pile put on, check sheet piles going along with the standard pile from start to finish. Once a defect is discovered adjust it asap.
After this checking, when in the transport and stacking, make sure not bend them, avoid the collision, in particular, do not break the continuous lockings. Stack space should be flat and solid not producing a large settlement. At the bottom of sheet pile stack, should pad wood blocks. Piles with different sections should be separated in different stacks, between each stacks should set aside certain channels to facilitate the moving for crane or transport vehicle.
没有评论:
发表评论